Call for tenders - Supply of brand-new solar systems (W)

Michel Daher Foundation (MDF) invites eligible companies to submit their tenders for the supply of brand-new solar systems for the Energy Audit to Improve Cost Efficiency for Industrialists project.

Lighting System

Item: LED Bulb

Specifications:

  • Capacity: 40 W
  • Color Temperature: 4000K – 5000K

Quantity: 23

 

Item: LED Projector

Specifications:

  • Capacity: 100 W
  • Color Temperature: 4000K – 5000K

Quantity: 2

 

Item: LED T5

Specifications:

  • Capacity: 18 W
  • Color Temperature: 4000K – 5000K

Quantity:18

 

Item: LED Bulb

Specifications:

  • Capacity: 9 W
  • Color Temperature: 4000K – 5000K

Quantity: 8

 

Item: Motion Sensors

Quantity: 10

 

Item: Electrical wires and components

Specifications: Old lighting bulbs were existing: no need for extensive wiring (needed wires are around 70 meters)

Quantity: LS

 

Item: Installation and Commissioning

Specifications:

  • Including Transportation and Mobilization
  • Including aftersales support for a complete year

Quantity: LS

 

Item: APS for Batteries

Specifications:

  • APS for Security System
  • Capacity: 2000 VA

Quantity: 1

 

Item: Installation and commissioning fees

Specifications: Including aftersales support for a complete year

Quantity: LS

 

Existing Solar System Rehabilitation

Item: Mounting Steel Structure

Specifications:

  • Existing steel structure (for 36 panels) does not comply with all safety measures, so it needs to be fortified.
  • Orientation shall be adjusted because the panels’ orientation in the meantime is not optimal.
  • Some of the panels (11) are north-oriented: to be adjusted as well.

 

Item: Electrical Works

Specifications:

  • Panels are not properly grouped or segmented into the strings: four strings exist in the meantime at 14, 13, 6, and 5 panels each respectively. This is to be optimized.
  • Fuse holders, fuses, DC breakers, and DC SPD are to be installed to all the strings (including all needed components and accessories).
  • SPD AC (4 poles) to be replaced.
  • The routing wires are not properly installed in many places, and they come into contact with steel wires and beams in several places. Some MC4 connectors are installed in areas that are highly exposed to rain and water: all of these are to be rectified. PV wires (6mm2)

Quantity: Around 370 meters

 

Item: Installation and commissioning fees

Specifications: 

  • Including aftersales support for a complete year
  • Including cleaning service for a complete year (a minimum of 4 visits)

Quantity: LS

 

Criteria to be included: 

  • Technical details and drawings
  • Reference List
  • CV
  • Warranty and maintenance
  • Delivery time
  • Adherence to H.R. 6256 the "Uyghur Forced Labor Prevention Act”

 

Call Type
Call for Tenders
Intervention Sectors
Science & Technology
How to Apply

 

Tenders are to be sent by email to info@daherfoundation.org 

Deadline
Countries
Lebanon