Ruwwad Al-Tanmeya is a regional non-profit community development organization that works with disenfranchised communities through education, youth volunteerism and grassroots organizing. Our approach encompasses an array of programs and projects that, together, strengthen initiative and facilitate redress to problems prioritized by members of the community.

Three main programs anchor Ruwwad: Child Development, Youth Organizing and Community Support. 

Three basic values shape every program or activity at Ruwwad Al-Tanmeya: secularism, diversity, and equity.

Objectives of this ToR:

Ruwwad seeks to design, engineer and build a scalable suspended solar system on the available space on its rooftop and other open spaces, to generate solar-power energy sufficient to run the building’s essential facilities for a minimum of 8h daily.

Deliverables:
  • Energy report.
  • EPC (Engineering, Procurement, Construction) activities.
  • Testing and Handover procedures.
Scope:

The awarded candidate’s scope of work will include:

  • Generate energy audit report
  • Take measurements and Generate CAD drawings
  • Design proper solar solution with simulation, designs, SLDs, datasheets and renders (if possible)
  • Procure necessary material and labor
  • Complete construction works as agreed upon with Ruwwad
  • Test solution
  • Perform training to assigned Ruwwad staff
  • Final handover and project sign-off.
Technical Specs:
  • Autonomy: 8h/day at least.
  • Solar Panels: to require minimal or no-maintenance, should be 2m*1m and should be able to deliver at least 300Wp for every panel. Both monocrystalline and polycrystalline are accepted, as well as any other technology available.
  • Batteries: Maintenance free or low maintenance batteries, can be Deep Cycle / Tubular, lithium based or others. Minimum lifetime of 5 years and/or 3000 cycles at 80% DoD. Battery casing should be weather sealed.
  • Inverter: efficiency above 95% with internal SPD, high MPPT and high power factor. Should include LED reading screen and should be IP65 protected at least.
  • Mount structure: metallic steel structure, to rise at least 2.2m above rooftop floor, and to withstand wind speeds up to 225 km/h
  • Backup time: 8h daily for the essential load at a minimum, without the need of an external power source such as generator or EDL

All material should be covered with warranty, respective datasheets and country of origin must be provided by awarded contractor for approval in due time.

All material should conform to local safety and power regulations.

Warranty Specs:

10 years on batteries, inverter and solar panels.

Execution Timeline:

Task

Expected Execution Time

Meetings with Ruwwad to inspect location and better understand the requirements

1 week

Generate Energy Audit Report

2 weeks

EPC Operations

2-3 months

complete testing, training and handover

1 week

 

Payment milestones:

% on energy audit report

% on finalization of design phase including approval on all designs, SLDs and datasheets and right before procurement

% on handover

% after 3 months of handover

Objectives of this ToR:

Ruwwad seeks to design, engineer and build a scalable suspended solar system on the available space on its rooftop and other open spaces, to generate solar-power energy sufficient to run the building’s essential facilities for a minimum of 8h daily.

Deliverables:
  • Energy report.
  • EPC (Engineering, Procurement, Construction) activities.
  • Testing and Handover procedures.
Scope:

The awarded candidate’s scope of work will include:

  • Generate energy audit report
  • Take measurements and Generate CAD drawings
  • Design proper solar solution with simulation, designs, SLDs, datasheets and renders (if possible)
  • Procure necessary material and labor
  • Complete construction works as agreed upon with Ruwwad
  • Test solution
  • Perform training to assigned Ruwwad staff
  • Final handover and project sign-off.
Technical Specs:
  • Autonomy: 8h/day at least.
  • Solar Panels: to require minimal or no-maintenance, should be 2m*1m and should be able to deliver at least 300Wp for every panel. Both monocrystalline and polycrystalline are accepted, as well as any other technology available.
  • Batteries: Maintenance free or low maintenance batteries, can be Deep Cycle / Tubular, lithium based or others. Minimum lifetime of 5 years and/or 3000 cycles at 80% DoD. Battery casing should be weather sealed.
  • Inverter: efficiency above 95% with internal SPD, high MPPT and high power factor. Should include LED reading screen and should be IP65 protected at least.
  • Mount structure: metallic steel structure, to rise at least 2.2m above rooftop floor, and to withstand wind speeds up to 225 km/h
  • Backup time: 8h daily for the essential load at a minimum, without the need of an external power source such as generator or EDL

All material should be covered with warranty, respective datasheets and country of origin must be provided by awarded contractor for approval in due time.

All material should conform to local safety and power regulations.

Warranty Specs:

10 years on batteries, inverter and solar panels.

Execution Timeline:

Task

Expected Execution Time

Meetings with Ruwwad to inspect location and better understand the requirements

1 week

Generate Energy Audit Report

2 weeks

EPC Operations

2-3 months

complete testing, training and handover

1 week

 

Payment milestones:

% on energy audit report

% on finalization of design phase including approval on all designs, SLDs and datasheets and right before procurement

% on handover

% after 3 months of handover

Call Type
Call for Tenders
Intervention Sectors
Children & Youth
Education
Training & Capacity Building
How to Apply
Bidding Instructions:

All bidders should bear the costs related to bidding to this ToR.

All bidders are required to present the following in their bid:

  • Commercial offer pertaining total quoted offer.
  • Technical offer
  • Letter of intent detailing who you are and how you intend to approach this project
  • Company profile including team size, team credentials, past projects, brand
  • MoF license no.
  • Has at least successfully delivered 3 similar projects
  • Reference letters

Please send any questions to Omar.Shammo@ruwwadaltanmeya.org by July 31st maximum. Answers will then be consolidated and shared with all candidates.

All bids to be sent to email omar.shammo@ruwwadaltanmeya.org July 31st 4.00PM max. Ruwwad will not consider any bids received after the deadline.

Bids should be sent via email only, with subject line “Suspended Solar System ToR – Bidder Name” and should carry two attachments, one technical and one commercial.

Field visit to be done on July 26th 2021, field visit is a must. All Q&A will be held on same day. Those who fail to attend will be disqualified.

Deadline
Countries
Lebanon