Skip to main content

RFQ-LBQZQ-23-0112/ Equipping water pumping station in Haour Taala with a Chlorination System operating on solar power

 

Terms Of Reference

Equipping water pumping station in Haour Taala with a Chlorination System operating on solar power

Haour Taala station - Baalbeck

Oxfam Lebanon Programme

 

Background

Oxfam is a global movement of people, working together to end the injustice of poverty through campaigning and responding to the needs of the poor. Oxfam has been working in Lebanon since 1993. We provide humanitarian assistance to vulnerable people affected by conflict, and we promote economic justice and good governance, and women’s rights. Oxfam also works with local partners to contribute to the protection and empowerment of marginalized women and men.

 

The project aims to equip a water pumping station located in Haour Taala with a chlorination system operating on solar power to provide chlorinated water to the community. The pump station supplies water to about 6,000 persons living in the village.

Objective

Design, supply and install a chlorination system and solar power to operate the chlorination system.

 

Rationale

In coordination with Bekaa Water Establishment (BWE) engineering team, Oxfam identified the need to install a chlorination system for Houar Taala water pumping station with a solar power system to run the electrical equipment of the chlorination system and ensure safe water supply to the community.

 

BWE should supply only safe chlorinated water, therefore equipping the water pumping station with a chlorination system is a key priority for BWE and the community. The availability of chlorination system and solar power will enable BWE to continue their services to people in need.

Location of Haour Taala pumping station: 33°54'34.5"N 36°09'15.6"E

Activity

Oxfam would like to hire supplier to install Gas Chlorination System operating on solar power in Haour Taala pump station. The supplier will design, supply, and install a PV (ON/OFF)- Hybrid system 4.4 kWp with battery autonomy (1 kW / 8 hours) a day. The works include construction of one concrete room 7m x 3.5m x 2.5m (divided into 3 rooms) one for the generator and fuel steel tank, one for the gas canisters and the last one for the dosing pump and network.

 

Also, the work involves the transfer of the generator and fuel tank from the old room to the new room.

 

Content of Works

  1. Design, supply and install Gas Chlorination System as per BoQ.
  2. Construction of a room for the generator, fuel tank, and chlorination system: 7m x 3.5m x 2.5m, divided into 3 rooms.
  3. Supply and install a total of 4,400 Wp PV system, Panels shall be of Monocrystalline type and from a well-known brand (supplier to provide datasheet).
  4. Supply and install Galvanized Steel structure for the Solar system. The steel structure shall be fixed on the roof of the station. (Supplier to provide datasheet).
  5. Supply & Installation of single-phase Hybrid inverter, high frequency, >5KW, 48VDC/220VAC, pure sine wave, with built-in dual input MPPT solar charger.
  6. Supply and installation of a battery bank Batteries, Lithium PO4, >8600Wh. @ 50% DOD (Supplier to provide datasheet).
  7. Supply and install all the DC & AC cables, battery cables, connectors, circuit breakers, panel board, protection devices, and accessories.
  8. Supply and install all the needed AC cables and accessories to connect selected loads such as lighting, Laptops, PC & printer sockets.
  9. Supply and install all the needed AC & DC circuit breakers, Surge Protectors, and all necessary protective devices
  10. Design, supervision, and final commissioning of the system within 1 year after-sales services.

 

 

All material documents shall be submitted for approval, all items to be of well-known brands. The offered system shall comply with the suggested BOQ but shall not be limited to the indicated equipment and devices. Any additional or complementary equipment or devices shall be included to ensure the right and complete operation of the system. The below BOQ is indicative.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Supply and installation of PV On/Off- Hybrid system 4.4 kWp with battery autonomy (1 kW/8 hours)

Item No

DESCRIPTION

UNIT

QTY

RATE

AMOUNT

Comments

 

Transportation and Installation of PV modules - Mono 545/555 Wp

PCS

8

USD

USD

 Total power shall be =>4.4 kWp

1

Galvanized supporting frame to install the modules on a flat roof- including supporting concrete pads- no floor fixation

LS

1

 

 

To be installed on top of chlorination room

2

Supply & Installation of single-phase Hybrid inverter, high frequency, >5KW, 48VDC/220VAC, pure sine wave, with built-in dual input MPPT solar charger.

PCS

1

 

 

 

3

Batteries, Lithium PO4, >8600Wh

PCS

1

 

 

 

>8 hours autonomy

4

DC & AC cables, battery cables and connectors

LS

1

 

 

 

5

Circuit breakers, panel board, protection devices, SPDs and accessories

LS

1

 

 

 

Type A+B SPD on both DC and AC sides

7

Design, supervision, and final commissioning of the system with 1 years after sales services

LS

1

 

 

 

 

 

 

 

 

 

 

 

TOTAL HT

 

 

 

 

 

 

VAT (11% )

 

 

 

 

 

 

TOTAL TTC

 

 

 

 

 

 

 

Gas Chlorination System

ITEM
Nb

DESCRIPTION

UNIT

QUANTITY

UNIT RATE USD

TOTAL AMOUNT USD

1

Chlorinator complete system (including pump, ejector, reregulation’s, auto-transfer switch, Cl2 flowmeter, gas masks…)

No.

1

 

 

2

Chlorine Cylinders (1 duty+1 standby+1 spare)

No.

3

 

 

3

Chlorine Leakage Detection System

No.

1

 

 

4

Ventilators and Shower

No.

2

 

 

5

Accessories (pipes, bends, tees, joints, bolts, nuts, supports, flow switch, vacuum switch…)

LS

1

 

 

6

Water sampling and physicochemical testing and analysis.

LS

1

 

 

 

Design, supervision, and final commissioning of the system including the production of a completion report and as-built drawings with 1 year after sales services

LS

1

 

 

 

Integration of the gas chlorination system with the submersible pump (PLC Programming)

LS

1

 

 

 

TOTAL TTC

 

 

 

 

 

 

Room for the Generator and Chlorination System

ITEM
Nb

DESCRIPTION

UNIT

QUANTITY

UNIT RATE USD

TOTAL AMOUNT USD

1

Construction of a Reinforced Concrete room (size 7m *3.5m*2.5m) divided into 3 rooms, (5m*3.5m, 2m*1.75m, 2m*1.75m)

 

 

 

 

1.1

Moving of existing generator and steel fuel tank to the new room.

Works shall include but not limited to:

  • Electric works dismantling and reinstallation
  • Fuel tank dismantling and reinstallation

LS

1

 

 

1.2

Construction of 1m*1m*0.3m footing

Works shall include but not limited to:

  • Excavation of pits, dimension = 1.2m*1.2m*0.5m
  • Installation of 2-way steel mesh Φ12mm spaced @20cm, side bend = 20cm
  • Installation of wood formwork
  • Casting ready mix concrete grade M25

Unit

6

 

 

1.3

Construction of tie Beams

Works shall include but not limited to:

  • Installation of wood formwork
  • Section = 20cm*40cm, Length = 3.5m
  • Installation of steel reinforcement: 4 horizontal Φ12 rebars, Φ8 stirrups spaced @ 20cm
  • Casting ready mix concrete grade M25

 

Unit

7

 

 

1.4

Construction of columns

Works shall include but not limited to:

  • Installation of wood formwork
  • Section = 60cm*20cm, Height = 2.5m
  • Installation of steel mesh: 6 vertical Φ12 rebars, Φ8 stirrups spaced @ 20cm
  • Casting ready mix concrete grade M25

Unit

6

 

 

1.5

Construction of floor slab

Works shall include but not limited to:

  • Installation of wood formwork
  • Dimension = 3.5*7 m
  • Installation of 2-way mesh reinforcement: Φ8 rebars spaced @ 20cm
  • Casting ready mix concrete grade M25
  • Curing finished surface

m2

25

 

 

1.6

Construction of hollow block roof slab

Works shall include but not limited to:

  • Installation of wood formwork with steel pillars reinforcement 
  • Dimension = 3.5*7 m
  • Embedded beam reinforcement:  4 horizontal Φ12 rebars, Φ8 stirrups spaced @ 20cm
  • Ribs reinforcement: 3 horizontal Φ12 rebars, Φ8 stirrups spaced @ 20cm
  • Casting ready mix concrete grade M25
  • Curing finished surface

LS

1

 

 

1.7

Construction of Hollow block walls:

Works shall include but not limited to:

  • Building 15cm-Hollow block wall
  • Cement pasting hollow blocks
  • Leveling walls

m2

62

 

 

1.8

Plastering hollow Block Walls

Works shall include but not limited to:

  • Spraying hollow block surface with cement paste
  • Plastering and leveling finish surface

m2

85

 

 

1.9

Paint Job

Works shall include but not limited to:

  • Surface preparation and leveling
  • Applying 1 base coat, acrylic polymer

 

85

 

 

 

TOTAL HT

 

 

 

 

 

VAT (11%)

 

 

 

 

 

TOTAL TTC

 

 

 

 

 

 

General Conditions

  • The period of execution of the works on the site shall be up to 20 working days from the date of handover of the site. daily penalty equivalent to 10% of the contract value if the contractor exceeds the specified working days. 
  • The contractor should prepare and submit a technical and financial offer for the works with details of the execution plan, detailed Bills of Quantities, and execution schedule.
  • The contractor must visit work sites before submitting his technical offer.
  • The tender items are not dividable.
  • The site engineer may amend what he deems "technically" suitable for the project and after taking the approval of Oxfam, and the Contractor must abide completely with the instruction of the supervising committee.
  • The Contractor’s relationship will directly be with OXFAM staff and not with the SDC
  • Oxfam shall give approval before installing any item, especially PV panels, Inverter, and batteries.
  • Oxfam Team or his/her representative is responsible to monitor and confirm the work.
  • Ensure safety and security/prevention to avoid any accident while implementing.
  • Oxfam has the right to increase or decrease quantities at the same unit cost and to request additional items.
  • Cleaning and removing the existing debris and unused materials from inside and around the site and transporting debris outside the site as directed by the engineer.

 

Contractor

  • The contractor must ensure that the supplied items are brand new and not renewed, and that applies to all the supplied items. Preference is given to the items that have proven technical quality and efficiency during the operation
  • The contractor is committed to all the engineering specifications.
  • Any unclarified items in the BOQ must be discussed with Oxfam staff.
  • Procedure of execution in the site will be shared with the contractor after signing the contract.

Selection criteria for administrative compliance

This part concerns the information given in the supplier questionnaire, each Bidding party can also include any other document he wishes, to assist us in judging their suitability according to the below criteria:

  • Company Profile.
  • At least Three years of experience in the same domain of construction (company name, contact name, and phone number).
  • Size of customer database - along with a list of your main customers including any Non-Governmental Organizations (NGOs) and U.N. agencies
  • Copies of Institution registration certificate and VAT registration certificate (if available) apply for companies only not individuals.

 

 

Pricing / Required Details

The prices must be presented according to the following titles:

  1. All tenderers must be qualified technically and financially to be able to submit their offers
  2. The unit prices and rates must be presented in US dollars for each of the offer items.

 

Coordination and Supervision

The activity will be supervised by Oxfam’s team. Oxfam may assign additional staff during the implementation of the activity.

 

Submission of offers

The field visit is expected to be on August 21, 2023 (MANDATORY)

Financial and Technical offers should be submitted to Oxfam after 2 working days after the site visit.

Expected start date Sep 11, 2023.

 

Questions / Request for clarification

Any requests for clarification may be submitted by email to eelkhoury@oxfam.org.uk ccing SHeneskehian@oxfam.org.uk

 

Timeframe and Payment

100% payment after completing the construction of the requested quantity and submitting the financial documents.

Call Type
Call for Consultancies
Organisation
Remuneration Range
> 6000 (USD)
Intervention Sectors
Water sanitation and hygiene
Duration of Contract
Detailed timeline per deliverable to be agreed upon with the consultant.
How to Apply
Deadline
Countries
Lebanon